Mayflower  Water Treatment AVK Projects Team

Mayflower water treatment works

AVK is valve partner on South West Water flagship project

September 2020 will mark the 400th anniversary of the Pilgrim Fathers’ intrepid journey from Plymouth to America aboard the Mayflower. The same pioneering spirit is reflected in South West Water’s new Mayflower water treatment works (WTW) which is due to become operational in autumn 2019. 

Located at Roborough, just north of Plymouth, Mayflower WTW uses a combination of suspended ion exchange, inline coagulation and membrane microfiltration to treat the water. It is the first time this combined technology has been used in the United Kingdom. Once it is fully operational the facility will have the capacity to produce up to 90 megalitres (90MLD) of high-quality drinking water every day.

The Mayflower WTW project took over six years from concept to completion, including two years of construction works on site. Over that period the AVK Projects team worked alongside South West Water and consulting engineers to ensure the correct valves were specified on the project. Valve specification was critical in ensuring the flow of water through the process was accurately regulated.

 
Mayflower  Water Treatment AVK Projects Case Study
Mayflower  Water Treatment AVK Butterfly Valves
Mayflower  Water Treatment Actuators

Through its global supply chain, AVK were able to provide a single source of supply across all valve products; AVK products used on the Mayflower WTW project include gate valves, butterfly valves, plug valves and non-return valves. The AVK Projects team also partnered with actuator specialists AUMA and Rotork to supply the specialist actuated valves.

The plug valves on the Mayflower WTW project were located at height. To simplify operational access, the valves were fitted with umbilical cords. The umbilical cords enabled the valves to be operated from ground level thereby eliminating the health and safety complications of working at height.

Mayflower WTW required seven kilometres of pipeline to connect to the existing South West Water mains network, including 1.6 km of pipeline installed using trenchless technologies to minimise impact on ancient woodland.

The AVK response was led by Stuart Montgomery, Water Projects Sales Manager:
‘Mayflower was a really exciting and challenging project. It drew on our extensive specialist engineering expertise of our projects team, built up over many years of working on utility projects both in the UK and worldwide. If the treatment technologies used at Mayflower are proved to be cost-effective then I can see them being replicated in other new WTW facilities. AVK Projects will be ideally placed to assist and advise on valve specifications and configuration if this is the case.’

To know more about the different types of valves used on this project click on the titles below:-

Small Diameter Gate Valves

Large Diameter Gate Valves

Butterfly Valves

Non-Return Valves

Eccentric Plug Valves

 

Contact Stuart about your project or follow the links below to download the brochure and learn more about the AVK Projects Team.

Mayflower Update December 2020

Mayflower Water Treatment Works Update

AVK valves play crucial role in South West Water’s landmark Mayflower water treatment works
AVK Water Projects Team

AVK Projects

Engineered Site Solutions

Water and Waste Water Solutions - project engineers and expertise
Engineered Water Projects Brochure

AVK Project Engineers and Expertise

Water and Waste Water Engineered Solutions